Massachusetts Bay Rapid Transit Authority
Steel shells by Wiley Manufacturing Co.
Praeger Kavanagh and Waterbury
73m
146m
12.3m
Project construction
1971-05-07
2
Two tubes; one track each
6.86m
11.4m
Selected as option to cofferdam method of crossing river. Transition sections in 29 m
dia compression ring cofferdam shafts.
dia compression ring cofferdam shafts.
Shipyard. Side launched.
At dockside near tunnel site
Lowered from pile-supported structures.
Tremie joint
Continuous steel shell.
Screeded foundation course.